Site Survey

After contracts are signed, the installer will come to your home to do a site survey where they will check your roof condition, obstructions, and ....

zoutside.PNG

The surveyor will check your utility meter's position in relation to where the solar panels will be placed so the design of the system can begin ...

The sales rep and the site surveyor will check your breaker box

to ensure it can safely handle solar... 

If an upgrade is needed, we will let you know.

Breaker Panel upgrades take 4-8 hours to complete,
and your electricity will be off during this time.

We will provide you with a hotel, if necessary for medical equipment, while this work is completed.

zelectrical.PNG
zAttic.PNG

The installer will check your attic trusses to ensure that your roof

has the structural integrity to handle the solar panel load.....
(one solar panel typically weighs > 45 lbs )

The tilt on your roof is checked.  

A roof tilt over 33 degrees requires extra safety equipment for the installers. 